What is allocation?

Allocation is the number of hours planned for a team member on a project. It represents the demand placed on their time.

What is utilization?

Utilization is the percentage of a team member’s available capacity that has been allocated.

Utilization = Allocated hours ÷ Available capacity × 100

Example

If a team member has 40 available hours and is allocated 30 hours, their utilization is 75%.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article

Contact our support team

Have more questions? Paid users can log in and email or chat with us.

Start your free trial