Overview of time and material projects

Created by Monica Madan, Modified on Mon, 29 Jan 2024 at 02:54 PM by Monica Madan

  • Plan Availability
  • Essential
  • Standard
  • Premium
  • Enterprise

Time and Material billing is a method of charging clients based on the actual hours worked. This approach is ideal for projects with constantly changing requirements, ensuring that clients are billed accurately for the hours reported. 


In this Article


Key concepts for navigating financials dashboard


Budgeted hours: When you create a project, you typically estimate or set a total number of hours that you expect it will take to complete the project as budgeted hours.


Allocated hours The total number of hours allocated for the project via resource management.


Tracked hours refers to the total number of hours that your team has tracked for the project. It represents the actual time spent working on the project and is reported using timesheets.


Budget is the notional revenue target for the project. The system will send you budget notifications based on this. 


Note:

  • Actual values are calculated based on the time tracked during the delivery of the project
  • Forecasted values are calculated based on the resource allocation plan for the project


ACTUALS 


Cost is calculated based on the hourly cost rate of your team members.

Hours tracked * Cost rates of respective team members/roles


Profit is the cost remaining from the revenue after covering all project costs

Revenue - Cost


Profit Margin is the ratio of profit to recognised revenue

(Profit/Revenue)*100



Forecasted 


Forecasted cost is Allocated hours * Cost rates


Forecasted profit is Forecasted revenue - Forecasted cost


Forecasted profit margin is (forecasted profit / forecasted revenue)*100


Accessing Financials for Time and Material projects


The financial dashboard gives you insights into your projects' real-time budget and time usage. The dashboard lets you compare the real-time utilization of your budget with the estimated budget and enables you to make necessary adjustments for the smooth running of the project.


To access Financials,


  • Navigate to Projects

  • Select a Fixed fee project you wish to view

  • Click on the Financials tab to track your project budget usage alongside the project hours.


Revenue Tracker

The Time and Material revenue tracker enables you to track revenue relative to the project budget and determine the remaining amount. 


Hours Tracker

The Budgeted hours tracker helps monitor tracked hours in comparison to the budgeted hours and identifies the remaining budgeted hours.



Progress Charts

With the progress chart, you can understand  data regarding how revenue recognised and hours usage has progressed for the project over time. This helps you compare the current progress with the planned trajectory of revenue and hours.


Revenue Progress

The progress charts provide you with information on the revenue recognised for the project over time.


X-axis is days.

Y-axis is revenue




Hours Progress

The progress charts provide you with information on the hours tracked for the project over time.


X-axis is days.

Y-axis is tracked hours



Breakdown charts

A Breakdown chart shows you the monthly breakdown of  revenue recognised and hours usage 

Revenue breakdown

Shows the monthly breakdown of forecasted and actual revenue recognised and the corresponding profit margin




Hours breakdown

Shows the monthly breakdown of billable and non-billable hours and the corresponding allocated hours




Summary Table

You can view the detailed summary of hours usage and cost for the overall duration of the project or on a granular monthly basis.


Revenue details table shows the detailed breakdown of revenue recognised and cost incurred for the project.




Hours details table shows the detailed breakdown tracked hours for the project.




Group by Roles and People Visualize the cost and hours utilized by each role and team member on the project


Group by Phases and tasks Visualize the cost and hours utilized by different phases and tasks in the project. 

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select atleast one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article

Contact our support team

Have more questions? Paid users can log in and email or chat with us.

Start your free trial